Republican Unitary Enterprise

Belarusian nuclear
power plant

Address:

Administrative and laboratory building (00UYA)

Vornyany village council, 2/7

Ostrovets district, Grodno region, Republic of Belarus 231220

Е-mail: belaes@belaes.by

NPP Information Center: ic@belaes.by

Phones:

Reception: +375 (1591) 4-53-59, fax: +375 (1591) 4-54-00

HR department: +375 (1591) 45-357; +375 (1591) 46-696

Accounts department: +375 (1591) 46-358

NPP Information Center: +375 1591 46 605

Thursday, 25 April 2019

Loading of fuel assembly simulators began at the first power unit of Belarusian NPP

Written by Department of information and public relations

In accordance with the schedule of work at the first power unit of Belarusian NPP, they started loading simulators of fuel assemblies into the reactor. This is one of the most important processes at the stage of preparation of the reactor installation for the cold and hot running.

The fuel assembly simulators are an exact copy of the fuel assemblies, fully replicate their design, but do not contain nuclear fuel. Они They are used instead of standard fuel assemblies during commissioning at the stage of cold and hot running in of the reactor facility.

As of April 25, 2019, about 75 of 163 are already loaded.

Last modified on Thursday, 25 April 2019
© 2010- State enterprise «Belarusian NPP». All rights reserved. At any use of materials of the web-site, the active reference is obligatory on www.belaes.by.
The web-site operates error-checking system. If you find a mistake, highlight it and press Ctrl + Enter.
Яндекс.Метрика
Development of CVR-Oktjabr'skij
Send a mistake message