On the 12th of January at 07.57 p.m. the Unit 1 of the Belarusian NPP has been started to work at the capacity nominal level.
The burning capacity is 3200 electrical megawatt, the electrical capacity is 1170 electrical megawatt. The dynamic/static testing has been continued according to the program of pilot commercial operation.
After the successful testing completion, the comprehensive equipment and system inspection of the power unit at the nominal capacity will be conducted during 15 days.
The power unit will be accepted to the commercial operation by the acceptance committee in due order after the successful completion of the comprehensive equipment inspection.