Print this page
Friday, 05 June 2020

In Zhlobin region, the implementation of projects continues as part of the integration of Belarusian NPP into the energy system

Written by Ministry of energy of the Republic of Belarus

In Zhlobin Electric Networks branch of RUE Gomelenergo, work continues on the implementation of two interrelated projects: the reconstruction of the 110 kV substation Diaproektor with the replacement of 10 kV switchgear cubicles, as well as the installation of electric boilers at Rogachev boiler room.

At the substation, the cells of the third and fourth sections of 10 kV were replaced and put into operation, the cells of the second 10 kV section were installed and commissioned. The cassette cells of the indoor unit manufactured by JSC Raton (Gomel) were installed. 

The need for reconstruction of the 110 kV substation “Diaproektor” is due to depreciation of equipment, the importance of improving the reliability of power supply to consumers in Rogachev, as well as the implementation of the project to install two electric boilers with a capacity of 20 MW each in the Rogachevskaya boiler house in Rogachev.

Currently, installation of heat storage tanks, installation of circulation and network pumps, sites and electric boilers are being carried out in the boiler room. A power transformer with a capacity of 10 MVA was dismantled and a site was prepared for the installation of a new power transformer with a capacity of 40 MVA. The general contractor is OJSC Elektrocentrmontazh. Work is scheduled to be completed in this September.

Last modified on Friday, 05 June 2020